Beijing Nangong Municipal Solid Waste Incineration Plant Comments and Addenda to the Feasibility Study



 

Under the theme of “Green Olympics” Beijing is undertaking considerable efforts to improve the municipal solid waste management (SWM) system. One component of the planned activities is the realization of a waste to energy (waste incineration) plant adjacent to the Nangong composting plant in the South of Beijing until 2008.

 

KfW, having already supported realization of the Nangong composting plant, is going to provide assistance for the Nangong incineration plant as well. In December 2004, Infrastruktur & Umwelt, was commissioned to assist Beijing Municipal Administration Commission (BMAC) in the preparation of the feasibility study.

Contact

Dipl.-Ing. Gernod Dilewski   




Our Services

Optimisation of the technical concept
Analysis of the current SWM situation in Beijing Municipality and integration of the incineration plant into the future SWM system
Assessment of socio-economic impact, financing and cost recovery
Preparation of documents and calculations regarding Clean Development Mechanisms (CDM)

Project data

Country:

China 

 

Location:

Beijing

 

Client:

BeijingMunicipal Administration Council (BMAC)

 

Financing:

KfW Entwicklungsbank

 

Value of contract:

200.000 EUR

 

Duration:

2004-ongoing